Legacy Drive

​Sam Rayburn Tollway (SRT) to Warren Parkway



Construction on Legacy Drive, from Sam Rayburn Tollway (SRT) to Warren Parkway, began July 6, 2021. Legacy Drive will be reconstructed and widened from a four-lane divided roadway to six lanes. Watch a Progress in Motion video on the Legacy Drive Widening Project.

Project Schedule


  • Start Date:  July 6, 2021
  • Preliminary Phase:  Construct temporary pavement and traffic signals (July 6 to mid-August 2021)
  • Phase 1:  All traffic switched to the southbound side; construction of the three new northbound lanes (mid-August 2021 to Spring 2022)
  • Phase 2:  All traffic switched to the newly constructed northbound lanes; construction of the three new southbound lanes (Spring 2022 to Winter 2022)
  • Final Phase: Traffic switched to the newly constructed northbound and southbound lanes; install lighting and landscaping; site cleanup (Winter 2022 to Spring 2023)
  • Expected Completion:  Spring 2023

Look Ahead Schedule

A three week look ahead schedule will outline the planned construction schedule and pertinent activities, including lane closures, associated with the project.

Week of July 19

*Single lane closures on northbound and southbound lanes may impact traffic from 9:00 a.m. to 4:00 p.m.*

The contractor will continue to construct temporary pavement to provide three southbound lanes during Phase 1, which includes the removal of remaining median trees. The inside northbound and southbound lanes will experience closures while trees are being removed. Construction of temporary traffic signals continues at Legacy Drive and Town and Country Boulevard; Legacy Drive and Country Club Boulevard; Legacy Drive and Stonebriar Drive.

Week of July 26

*Single lane closures on northbound and southbound lanes may impact traffic from 9:00 a.m. to 4:00 p.m.*

The contractor will finalize the subgrade prep work and start paving the temporary lane. Construction of the temporary traffic signals will continue, with an estimated completion by mid-August.

Week of August 2

*Single lane closures on northbound and southbound lanes may impact traffic from 9:00 a.m. to 4:00 p.m.*

The contractor will finalize the subgrade prep work and start paving the temporary lane. Construction of the temporary traffic signals will continue, with an estimated completion by mid-August.


Notes Concerning Construction Activity

Construction schedules change, sometimes with little notice, for any number of reasons. Please understand there will be changes. We appreciate your patience.

Construction work is dependent on the weather. The information we provide regarding all construction timelines and activities is weather permitting which means the work is anticipated to happen in that timeframe or the next available date when the weather allows. Rain will cancel most construction activity. In addition, certain activities require specific temperatures or dry weather for a previous number of days before execution.

Capital Improvements Project Dashboard


Keep up to date on all capital improvement projects currently active within the City of Frisco Engineering Services and Public Works Departments. The interactive map displays project locations, general construction timeframes and estimated construction costs.

View the CIP Dashboard here.

Landscape Gallery

The project will incorporate the new median landscaping standards which include drought tolerant plants and trees born in Texas. As one of the gateways to Frisco, the corridor near SH 121 and Legacy Drive will showcase some of these plants. View the Landscape Design Plans here.