Intersection Improvements
This project will add lanes to improve capacity at seven (7) of the highest volume intersections in Frisco. The follow improvements will also be included:
- street lighting
- traffic signal adjustments
- storm drains
- sidewalks
- landscaping and irrigation adjustments associated with the roadway widenings
Project Timeline
- Lebanon Road / FM 423 - August start date; Work continues through October
- Main Street / Preston Road - Week of October 2nd start date
- Wade Boulevard / Preston Road
- Coit Road / SH 121
- Ohio Drive / Hillcrest Road
- Stonebrook Parkway / FM 423
- Warren Parkway / Preston Road
The extension of Donnie Mayfield Way is also part of this project. The extension will reach the future site of an elevated storage tank on PGA Parkway.
Anticipated completion of all seven (7) intersections is Q2 2025.
Lane closures are anticipated between 9 a.m. and 3:30 p.m. daily in an effort to keep existing lanes open during peak travel times. Please slow down and use caution in the work zone.
Main Street / Preston Road
Construction is anticipated to begin the first week in October.
Lebanon Road / FM 423
Construction continues on the intersection improvements at Lebanon Road and FM 423.
Capital Improvements Project Dashboard
Keep up to date on all capital improvement projects active within the City of Frisco Engineering Services Department. The interactive map displays project locations, general construction timeframes and estimated construction costs. View the CIP Dashboard here.
Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project Dashboard Capital Improvements Project DashboardCapital Improvements Project Dashboard
Notes Concerning Construction Activity
Construction schedules change, sometimes with little notice, for any number of reasons. Please understand there will be changes. Construction work is dependent on the weather. Information regarding all construction timelines and activities is weather permitting. Rain will cancel most construction activity. In addition, certain activities require specific temperatures or dry weather for a previous number of days before execution. We appreciate your patience. Capital Improvements Project Dashboard Capital Improvements Project Dashboard